I don’t have a natural gas installation in my building or home
What are the steps I must follow to enjoy natural gas?
Paso
Request connection to the natural gas network
Check if your home is within the Nedgia distribution area and request a connection.
Paso
Accept the connection conditions
Once you have requested a connection, within 6 days, you will receive an e-mail from Nedgia with the following information:
Estimate period for the construction of the network.
Map / sketch of the connection point.
Applicant’s connection fee budget
Request for natural gas in the building
If you agree, you must accept the proposal by sending the requested documentation by e-mail to Nedgia.
Once we have received it, we will start the connection process.
Paso
Performs the installation of natural gas
Natural gas must be installed by an authorised installer, who will issue Nedgia with the corresponding certificate so that your home can be connected to the natural gas network.
Contact your trusted installer or, if you prefer, consult the list of installer associations.
Paso
Contract the natural gas supply
Once your installation is connected to the gas network, you can manage the natural gas supply contract with a supply company.
> List of supply companies
> Power offer comparison engine
> Costs associated with contracting the supply of natural gas
Paso
Commissioning
When the supply company contacts us to request the start of your supply, at Nedgia we will contact you to arrange a visit from a technician to check that your installation complies with current regulations, put in the gas meter, and get everything ready so that you can start enjoying natural gas.